Photovoltaic power plant from preparation to completion - the whole process details
1.Pre-project inspection
Examination of the project terrain and roof resources, the surrounding environmental conditions such as: transportation, procurement of materials, labor in the market, roads, water and electricity.
Grid structure and annual load, capacity of consuming load, voltage level of access system, verification of access interval, conditions of length corridor of sending out lines, and policy of local grid company.
2.Pre-construction information and approval documents of the project
①commission a qualified unit to do large-scale PV grid-connected power plant project for feasibility study analysis, project filing application report.
②Enter the filing list of your province (city)
③ Proceed with the construction project bank fund certificate (not less than Obtained by the relevant provincial/municipal departments 20% of the total investment in the project)
Approval document or loan agreement (not higher than the total project investment) Letter of intent to obtain a loan between the construction project and the bank 80%)
④Commissioning qualified units to do the project design to obtain permission from the Construction Bureau to start work where the project is to be constructed
3.Approval of documents
1
Provincial Power Company
Grid connection approval document
Land pre-approval opinion
2
Provincial Land Department
Letter of Important Mineral Resources Not Overburdened
Geological Hazard Assessment Filing Registration Form
3
Provincial Construction Department
Site selection opinion letter and site selection planning opinion
Site selection opinion letter (some places do not have this)
4
Provincial/municipal cultural relics department
Required)
5
Provincial/municipal environmental protection department
Approval of Environmental Impact Report Form
6
Provincial/municipal safety supervision bureau
Approval of Safety Evaluation Form
7
Provincial/municipal water conservancy department
Approval of Soil and Water Conservation Program
4.Project construction drawing design
①Site mapping, ground survey, boundary survey, and qualification Design requirements②Access system report preparation and review at the meeting
③Produce general construction blueprints Drawings for each specialty (structural, civil, electrical, etc.)construction, electrical, etc.) ④Out of the product specifications (as equipment) ⑤Procurement bidding basis) ⑥Sign technical agreement with each manufacturer
⑦On-site technical exchanges, drawing review ⑧Send out the line preliminary design review at the meeting out of the power grid intention
5.Project implementation and construction
Material Bidding and Procurement
Modules, inverters, convergence boxes, DC distribution cabinets, brackets, box-type transformers, etc.
equipment, etc.
1. Foundation pouring
2. Installation of racking, PV modules, convergence boxes, etc.
3. Inverter room, box-type transformer foundation construction
Construction of power generation area
4. Installation and commissioning test of equipment for box-type transformer, inverter, DC cabinet and communication cabinet
5. Electrical connection and cable laying (between components, components and convergence boxes, convergence boxes and DC cabinets, DC cabinets, etc.)
Electrical connection and cable laying (between modules, modules and convergence box, convergence box and DC cabinet, DC cabinet and inverter, inverter and box variable),
Welding of the whole field grounding production, road construction in the power generation area.